Hou Taiwan regions supporting infrastructure recycled water project
Project stage: construction design (2013-11-8, the project is bidding for design unit. For details, please read Hou Taiwan regions supporting infrastructure recycled water project Tender Notice (2013-11-7). The design unit is expected to be determined in early December 2013)
Major equipment: grill, pumps, piping, pipes, valves, automation control systems, submersible pumps, cranes, lightning protection and grounding, flow meters, transmitters, ozone generators, trans fishing grate discharge machine. (For reference only)
Project Description: The project is located in Houtai Tianjin, including Xiangze Road , Kaiyuan Road, Xiangya Road , Hengda Road, Bao Zexi Road , Chunming Road, Wenzheng Road, Zhongda Road, qingli Road, Xiangyi Road, 10 roads of recycled water project. The total length of the roads is about 15,292 meters; the maximum diameter of recycled water pipeline is DN1000mm.
The total investment is 51.91 million yuan.